A new electrical room layout shows a casework run proposed beside a panelboard. What is the best coordination action before releasing the wall and casework layout?
Correct Answer
B) Reserve the required clear working space around the panelboard and keep it free of permanent obstructions
Panelboard locations must be coordinated so qualified workers have clear access for operation, inspection, and maintenance. The key construction-manager action is preserving electrical working space before walls and casework become fixed; the other choices confuse door swing or egress with equipment access, or defer a coordination problem until rework is likely.
Why This Is the Correct Answer
Panelboard locations must be coordinated so qualified workers have clear access for operation, inspection, and maintenance. The key construction-manager action is preserving electrical working space before walls and casework become fixed; the other choices confuse door swing or egress with equipment access, or defer a coordination problem until rework is likely.
Why the Other Options Are Wrong
Option A: The coordinator should approve the layout if the panel door can still swing open
A swinging cover does not prove a worker has clear space to stand, inspect, operate, and service the panel; door movement is only one small part of the access issue.
Option C: Let the electrical contractor shift the panel after finishes are complete if the casework blocks access
Waiting until finishes are complete turns a layout conflict into rework and may leave the panel trapped by permanent construction.
Option D: The coordinator should use the corridor egress width as the only access check
Corridor egress width is a life-safety path check; it does not replace the electrical equipment access space needed at the panel.
Memory Technique
Remember electrical equipment access coordination by its jobsite consequence: the correct move points to Reserve the required clear working space around the panelboard and keep it free of permanent obstructions.
Reference Hint
Open Mechanical and Electrical Systems for Construction Managers, 4th Ed., 2024; use by topic index - electrical equipment access / panelboards to confirm that Panelboard locations must be coordinated so qualified workers have clear access for operation, inspection, and maintenance.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass