EstatePass
NASCLAWoodmedium4% of exam part

A gypsum board scope requires 180 sheets before waste. With 7 percent waste, how many sheets should be carried?

Correct Answer

B) 193 sheets

Sheets with waste are 180 x 1.07 = 192.6, rounded up to 193 sheets.

Answer Options
A
187 sheets
B
193 sheets
C
200 sheets
D
207 sheets

Why This Is the Correct Answer

Sheets with waste are 180 x 1.07 = 192.6, rounded up to 193 sheets.

Why the Other Options Are Wrong

Option A: 187 sheets

gypsum sheet waste, choice a: 187 sheets implies about 3.89% waste on 180.

Option C: 200 sheets

gypsum sheet waste, choice c: 200 sheets is wrong because 200 sheets implies about 11.11% waste on 180.

Option D: 207 sheets

gypsum sheet waste, choice d: 207 sheets implies about 15% waste on 180.

Memory Technique

Say the gypsum sheet waste rule aloud as a chain; the chain ends at 193 sheets, not an intermediate stop.

Reference Hint

Open Gypsum Construction Handbook, 7th Ed., 2014; use the index entry or section for "Gypsum Construction Handbook - board types / layout / quantity" to confirm that Sheets with waste are 180 x 1.07 = 192.6, rounded up to 193 sheets.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.