An activity was planned to finish on day 42 but actually finished on day 47. What is the finish variance?

Correct Answer

A) 5 days late

Finish variance is 47 - 42 = 5 days late.

Answer Options
A
5 days late
B
5 days early
C
47 days late
D
42 days late

Why This Is the Correct Answer

Finish variance is 47 - 42 = 5 days late.

Why the Other Options Are Wrong

Option B: 5 days early

schedule variance days, choice a: 5 days early repeats the numeric result but changes the required label or rounding.

Option C: 47 days late

schedule variance days, choice b: 47 days late is produced by 47. The error is using that partial/alternate setup.

Option D: 42 days late

schedule variance days, choice d: the number 42 days late comes from 42 but stops before the calculation reaches 5 days late.

Memory Technique

Picture a weep path labeled schedule variance days: finish every operation before accepting 5 days late.

Reference Hint

Open Construction Jobsite Management, 5th Ed. (2024); use by topic index - duration / float / baseline / updating / variance to confirm that Finish variance is 47 - 42 = 5 days late.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.