The earthwork section requires unit prices for unsuitable-soil removal. What is the contract-administration use of those unit prices?
Correct Answer
C) They adjust payment when the measured quantity differs from the bid quantity under the contract
Unit prices establish agreed pricing for measured quantity changes in defined work. Other choices overstate unit prices, make them internal only, or eliminate the measurement that makes unit pricing work.
Why This Is the Correct Answer
Unit prices establish agreed pricing for measured quantity changes in defined work. Other choices overstate unit prices, make them internal only, or eliminate the measurement that makes unit pricing work.
Why the Other Options Are Wrong
Option A: Use unit prices to replace all lump-sum work as though it satisfied the specific unit prices requirement
Choice A gives They replace all lump-sum work. Its specific error: it removes the controlling Unit prices requirement instead of meeting it.
Option B: Use unit prices only to ank subcontractors internally
Choice B (They are used only to rank subcontractors internally) is rejected because it tries to bypass the Unit prices checkpoint.
Option D: Use unit prices to waive the need for field measurement
The trap in D is They waive the need for field measurement. That selection is wrong because it removes the controlling Unit prices requirement instead of meeting it.
Memory Technique
Treat unit prices like a labeled shelf; only the matching condition belongs with They adjust payment when the measured quantity differs from the bid quantity under the contract.
Reference Hint
Open Construction Project Management, 5th Ed. (2022); use the index entry or section for "Unit-price work and quantity adjustments" to confirm that Unit prices establish agreed pricing for measured quantity changes in defined work.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
