The earthwork section requires unit prices for unsuitable-soil removal. What is the contract-administration use of those unit prices?

Correct Answer

C) They adjust payment when the measured quantity differs from the bid quantity under the contract

Unit prices establish agreed pricing for measured quantity changes in defined work. Other choices overstate unit prices, make them internal only, or eliminate the measurement that makes unit pricing work.

Answer Options
A
Use unit prices to replace all lump-sum work as though it satisfied the specific unit prices requirement
B
Use unit prices only to ank subcontractors internally
C
They adjust payment when the measured quantity differs from the bid quantity under the contract
D
Use unit prices to waive the need for field measurement

Why This Is the Correct Answer

Unit prices establish agreed pricing for measured quantity changes in defined work. Other choices overstate unit prices, make them internal only, or eliminate the measurement that makes unit pricing work.

Why the Other Options Are Wrong

Option A: Use unit prices to replace all lump-sum work as though it satisfied the specific unit prices requirement

Choice A gives They replace all lump-sum work. Its specific error: it removes the controlling Unit prices requirement instead of meeting it.

Option B: Use unit prices only to ank subcontractors internally

Choice B (They are used only to rank subcontractors internally) is rejected because it tries to bypass the Unit prices checkpoint.

Option D: Use unit prices to waive the need for field measurement

The trap in D is They waive the need for field measurement. That selection is wrong because it removes the controlling Unit prices requirement instead of meeting it.

Memory Technique

Treat unit prices like a labeled shelf; only the matching condition belongs with They adjust payment when the measured quantity differs from the bid quantity under the contract.

Reference Hint

Open Construction Project Management, 5th Ed. (2022); use the index entry or section for "Unit-price work and quantity adjustments" to confirm that Unit prices establish agreed pricing for measured quantity changes in defined work.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.