The earthwork section requires unit prices for unsuitable-soil removal. What is the contract-administration use of those unit prices?
Correct Answer
C) They adjust payment when the measured quantity differs from the bid quantity under the contract
Unit prices establish agreed pricing for measured quantity changes in defined work. Other choices overstate unit prices, make them internal only, or eliminate the measurement that makes unit pricing work.
Why This Is the Correct Answer
Unit prices establish agreed pricing for measured quantity changes in defined work. Other choices overstate unit prices, make them internal only, or eliminate the measurement that makes unit pricing work.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
A rooftop unit schedule lists capacity in tons of cooling. In HVAC estimating, one ton of cooling equals what heat-transfer rate?
The bid form asks for a base bid and three alternates. How should the contractor submit alternate pricing?
A specification includes a $40,000 hardware allowance because final selections are pending. How is the allowance treated in the bid?
Before the first progress payment, the owner requests a schedule of values. What is its main contract-payment function?
A signed change order is issued for added lobby millwork. Which contract effect should it state?
On the finish plan, locate room R358; then use the finish schedule. What remarks is listed?
The owner needs a scope change to proceed before price and time are fully agreed. Which instrument is used to direct the change while reserving later adjustment?