A drywall lid is about to conceal junction boxes that contain splices, and no access panels are shown. What should be coordinated before the ceiling is closed?
Correct Answer
D) Relocate the boxes or provide access so splices remain accessible
Junction boxes containing splices must remain accessible after installation. Other choices document or hide the condition rather than preserving access for inspection and maintenance.
Why This Is the Correct Answer
Junction boxes containing splices must remain accessible after installation. Other choices document or hide the condition rather than preserving access for inspection and maintenance.
Why the Other Options Are Wrong
Option A: Photograph the boxes and cover them permanently
A photograph records the hidden location but does not let inspectors or maintenance workers reach the splices later.
Option B: Move the splices into flexible conduit above the ceiling and leave the junction boxes concealed
Flexible conduit is a raceway, not an access method for concealed splices; the splice location still must be reachable.
Option C: The coordinator should paint the box covers the ceiling color
Painted covers blend into the ceiling visually, but the issue is physical access, not appearance.
Memory Technique
Use the phrase "problem, control, result" for junction box accessibility; the result side is Relocate the boxes or provide access so splices remain accessible.
Reference Hint
Open Mechanical and Electrical Systems for Construction Managers, 4th Ed., 2024; use by topic index - raceways / EMT / junction boxes to confirm that Junction boxes containing splices must remain accessible after installation.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass