A gable roof covers a 60 ft by 40 ft rectangular plan. The slope factor for the 6:12 roof is 1.118. Before waste, how many roofing squares are needed?
Correct Answer
B) 26.8 squares
Plan area is 60 x 40 = 2,400 sf. Sloped roof area is 2,400 x 1.118 = 2,683 sf. Roofing squares are 2,683/100 = 26.8 squares. Other choices use plan area only, add waste not requested, or round to an unsupported value.
Why This Is the Correct Answer
Plan area is 60 x 40 = 2,400 sf. Sloped roof area is 2,400 x 1.118 = 2,683 sf. Roofing squares are 2,683/100 = 26.8 squares. Other choices use plan area only, add waste not requested, or round to an unsupported value.
Why the Other Options Are Wrong
Option A: 24.0 squares
sloped roof area, choice a: 24.0 squares backs into 0.89 when divided by 2683/100; the accepted setup gives 1 on that same base.
Option C: 29.5 squares
sloped roof area, choice c: 29.5 squares backs into 1.1 when divided by 2683/100; the accepted setup gives 1 on that same base.
Option D: 30.0 squares
sloped roof area, choice d: 60 x 6 / 12 gives 30.0 squares. That calculation follows multiplies two values and divides by the third.
Memory Technique
Keep a tag beside sloped roof area: if one number is skipped, the option drifts away from 26.8 squares.
Reference Hint
Open Roofing Construction and Estimating, Atcheson, 1995/2022 reprint; use the index entry or section for "Roof area and roofing square calculation" to confirm that Plan area is 60 x 40 = 2,400 sf.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?