A solid-web diagonal brace is being installed for frame stability during steel erection. What minimum bolt condition does OSHA allow at each brace connection?
Correct Answer
A) At least one bolt per connection drawn up wrench-tight
OSHA 1926.756(b) allows solid web structural members used as diagonal bracing to be secured by at least one bolt per connection drawn up wrench-tight, or the equivalent specified by the structural engineer of record. Other choices overstate, understate, or replace the OSHA condition.
Why This Is the Correct Answer
OSHA 1926.756(b) allows solid web structural members used as diagonal bracing to be secured by at least one bolt per connection drawn up wrench-tight, or the equivalent specified by the structural engineer of record. Other choices overstate, understate, or replace the OSHA condition.
Why the Other Options Are Wrong
Option B: Two fully pretensioned bolts at each connection
In metals work, Two fully pretensioned bolts at each connection is the wrong selection for Diagonal bracing: the choice would not get the project to A.
Option C: Treat the condition as requiring no bolts if a tack weld is present
The trap in C is No bolts if a tack weld is present. That selection is wrong because the option does not produce the required Diagonal bracing outcome, A.
Option D: Set the diagonal bracing threshold at Four bolts before any fit-up load is released
Choice D gives Four bolts before any fit-up load is released. Its specific error: it points to Four bolts before any fit-up load is released, but.
Memory Technique
Link diagonal bracing to its book condition; a different condition means a different answer than At least one bolt per connection drawn up wrench-tight.
Reference Hint
Open 29 CFR Part 1926, Subpart R - Steel Erection; use 29 CFR 1926.756(b) to confirm that OSHA 1926.756(b) allows solid web structural members used as diagonal bracing to be secured by at least one bolt per connection drawn up wrench-tight, or the equivalent specified by the structural engineer of record.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?