A low-slope roof takeoff measures 18,400 sf of membrane field area. The estimator adds 7 percent for laps, perimeter waste, and detailing. What order area should be carried?
Correct Answer
C) 19,688 sf
Adjusted order area is 18,400 x 1.07 = 19,688 sf. Other choices add only 7 sf, subtract the allowance, or use a 10 percent allowance instead of the stated 7 percent.
Why This Is the Correct Answer
Adjusted order area is 18,400 x 1.07 = 19,688 sf. Other choices add only 7 sf, subtract the allowance, or use a 10 percent allowance instead of the stated 7 percent.
Why the Other Options Are Wrong
Option A: 18,407 sf
roof waste allowance, choice b: 18,407 sf is produced by 18,400. The error is using that partial/alternate setup.
Option B: 17,112 sf
roof waste allowance, choice c: 18,400 x 0.93 gives 17,112 sf. That calculation follows multiplies those two listed numbers.
Option D: 20,240 sf
roof waste allowance, choice d: 20,240 sf adds an extra unstated add-on/subtraction; the numeric gap is 552.
Memory Technique
Say the roof waste allowance rule aloud as a chain; the chain ends at 19,688 sf, not an intermediate stop.
Reference Hint
Open Roofing Construction and Estimating, Atcheson, 1995/2022 reprint; use the index entry or section for "Membrane roof material allowance" to confirm that Adjusted order area is 18,400 x 1.07 = 19,688 sf.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A fixed storefront lite has exposed area over 9 sf, its bottom edge is 12 in. above the floor, its top edge is above 36 in., and a walking surface is within 36 in. horizontally. What IBC glazing condition is met?
Next Question
Which statement correctly separates an alternate from a substitution?