A fixed storefront lite has exposed area over 9 sf, its bottom edge is 12 in. above the floor, its top edge is above 36 in., and a walking surface is within 36 in. horizontally. What IBC glazing condition is met?
Correct Answer
A) A hazardous location requiring safety glazing
IBC 2406 identifies large fixed or operable glazing as hazardous where the pane exceeds 9 sf, bottom edge is less than 18 in. above the floor, top edge is more than 36 in. above the floor, and a walking surface is within 36 in. horizontally. Other choices ignore the four-part hazardous-location test.
Why This Is the Correct Answer
IBC 2406 identifies large fixed or operable glazing as hazardous where the pane exceeds 9 sf, bottom edge is less than 18 in. above the floor, top edge is more than 36 in. above the floor, and a walking surface is within 36 in. horizontally. Other choices ignore the four-part hazardous-location test.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
A rooftop unit schedule lists capacity in tons of cooling. In HVAC estimating, one ton of cooling equals what heat-transfer rate?
The bid form asks for a base bid and three alternates. How should the contractor submit alternate pricing?
A specification includes a $40,000 hardware allowance because final selections are pending. How is the allowance treated in the bid?
The earthwork section requires unit prices for unsuitable-soil removal. What is the contract-administration use of those unit prices?
Before the first progress payment, the owner requests a schedule of values. What is its main contract-payment function?
A signed change order is issued for added lobby millwork. Which contract effect should it state?
On the finish plan, locate room R358; then use the finish schedule. What remarks is listed?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
On the mechanical plan, find equipment tag EF-11; then read the equipment schedule. What notes is shown?
Next Question
A low-slope roof takeoff measures 18,400 sf of membrane field area. The estimator adds 7 percent for laps, perimeter waste, and detailing. What order area should be carried?
