Which statement correctly separates an alternate from a substitution?
Correct Answer
A) An alternate is a separately priced bid item; a substitution is a proposed different product or method requiring approval
An alternate is separately priced as part of bidding, while a substitution proposes a different product or method for review. Other choices ignore review and bid structure.
Why This Is the Correct Answer
An alternate is separately priced as part of bidding, while a substitution proposes a different product or method for review. Other choices ignore review and bid structure.
Why the Other Options Are Wrong
Option B: Both always occur only after final payment
The trap in B is Both always occur only after final payment. That selection is wrong because the option delays or omits the controlling step.
Option C: Classify it as a substitution is never reviewed
Choice C gives A substitution is never reviewed. Its specific error: the option does not produce the required Alternate versus substitution outcome, An alternate is a separately priced bid item; a substitution is a proposed different product or method.
Option D: Treat the alternate as deleting every base-bid requirement
Choice D (An alternate deletes every base-bid requirement) is rejected because the option tries to substitute, waive, or delete the Alternate versus substitution control; the item instead requires An alternate is a separately priced bid item; a substitution is a proposed different product or.
Memory Technique
Keep alternate versus substitution as a cause-to-effect card with An alternate is a separately priced bid item; a substitution is a proposed different product or method requiring approval on the back.
Reference Hint
Open Construction Project Management, 5th Ed. (2022); use the index entry or section for "Alternates and substitutions" to confirm that An alternate is separately priced as part of bidding, while a substitution proposes a different product or method for review.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A low-slope roof takeoff measures 18,400 sf of membrane field area. The estimator adds 7 percent for laps, perimeter waste, and detailing. What order area should be carried?
Next Question
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
