A lift is used productively for 5.5 hours during an 8-hour shift. What is the utilization?

Correct Answer

D) 68.8%

Utilization is 5.5 / 8 = 0.6875 = 68.8%.

Answer Options
A
31.3%
B
55%
C
80%
D
68.8%

Why This Is the Correct Answer

Utilization is 5.5 / 8 = 0.6875 = 68.8%.

Why the Other Options Are Wrong

Option A: 31.3%

equipment utilization, choice a: 31.3% omits a required add-on/subtraction; the numeric gap is 37.5.

Option B: 55%

equipment utilization, choice b: 55% backs into 80 when divided by 0.6875; the accepted setup gives 100.07 on that same base.

Option C: 80%

equipment utilization, choice d: 80% backs into 128 when divided by 5 / 8; the accepted setup gives 110.08 on that same base.

Memory Technique

Store equipment utilization with its last math move; nearby answers are usually unfinished versions of 68.8%.

Reference Hint

Open Construction Jobsite Management, 5th Ed. (2024); use by topic index - labor hours / productivity / earned value / job cost to confirm that Utilization is 5.5 / 8 = 0.6875 = 68.8%.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.