NASCLAProcurement and Contracting Requirementsmedium

A $50,000 flooring allowance is included in the contract. The approved actual flooring cost is $43,500. What contract adjustment reconciles the allowance before markup terms?

Correct Answer

B) $6,500 deduct

The actual cost is $50,000 - $43,500 = $6,500 below the allowance, so the reconciliation is a $6,500 deduct before any contract markup terms. Other choices reverse the direction or use the full allowance.

Answer Options
A
$6,500 add
B
$6,500 deduct
C
$43,500 deduct
D
$50,000 add

Why This Is the Correct Answer

The actual cost is $50,000 - $43,500 = $6,500 below the allowance, so the reconciliation is a $6,500 deduct before any contract markup terms. Other choices reverse the direction or use the full allowance.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.