EstatePass
NASCLAGeneral Reqmedium22% of exam part

A site recorded 12 near misses over 60,000 labor-hours. Using a 200,000-hour base, what near-miss rate is reported?

Correct Answer

A) 40.0

Near-miss rate is 12 x 200,000 / 60,000 = 40.0.

Answer Options
A
40.0
B
20.0
C
24.0
D
72.0

Why This Is the Correct Answer

Near-miss rate is 12 x 200,000 / 60,000 = 40.0.

Why the Other Options Are Wrong

Option B: 20.0

near-miss rate, choice a: 20.0 backs into 6 when divided by 200000 / 60000; the accepted setup gives 12 on that same base.

Option C: 24.0

near-miss rate, choice c: 24.0 backs into 0.6 when divided by 40.0; the accepted setup gives 1 on that same base.

Option D: 72.0

near-miss rate, choice d: 72.0 backs into 1.8 when divided by 40.0; the accepted setup gives 1 on that same base.

Memory Technique

Remember near-miss rate as "base, adjustment, final unit"; the last unit should read 40.0.

Reference Hint

Open 29 CFR Part 1926 (OSHA Construction Standards), 1926-2023 / PSI OSHA Excerpts 2025; use OSHA reporting / recordkeeping topic to confirm that Near-miss rate is 12 x 200,000 / 60,000 = 40.0.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.