Three submittals were returned in 6, 9, and 12 days. What was the average turnaround?

Correct Answer

A) 9 days

Average turnaround is (6 + 9 + 12) / 3 = 9 days.

Answer Options
A
9 days
B
6 days
C
10 days
D
27 days

Why This Is the Correct Answer

Average turnaround is (6 + 9 + 12) / 3 = 9 days.

Why the Other Options Are Wrong

Option B: 6 days

submittal turnaround average, choice a: the number 6 days comes from 6 but stops before the calculation reaches 9 days.

Option C: 10 days

submittal turnaround average, choice c: 10 days backs into 3.33 when divided by 3; the accepted setup gives 3 on that same base.

Option D: 27 days

submittal turnaround average, choice d: 6, + 9, + 12 gives 27 days. That calculation adds three listed values.

Memory Technique

Remember submittal turnaround average as "base, adjustment, final unit"; the last unit should read 9 days.

Reference Hint

Open Construction Jobsite Management, 5th Ed. (2024); use by topic index - documentation / submittals / RFIs / closeout to confirm that Average turnaround is (6 + 9 + 12) / 3 = 9 days.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.