Stored ceiling tile pallets are placed directly in front of a switchgear lineup on the day of startup. What should the superintendent require before energization work proceeds?
Correct Answer
A) Remove the stored material and restore the required electrical working space
Clear the pallets and maintain the required access and working space before startup work. Visible handles alone do not make an obstructed workspace usable, and noncombustible carts can obstruct it too. OSHA prohibits using the required working space for storage; the applicable dimensions depend on the equipment and conditions. Source: https://www.osha.gov/laws-regs/regulations/standardnumber/1926/1926.403
Why This Is the Correct Answer
Clear the pallets and maintain the required access and working space before startup work. Visible handles alone do not make an obstructed workspace usable, and noncombustible carts can obstruct it too. OSHA prohibits using the required working space for storage; the applicable dimensions depend on the equipment and conditions. Source: https://www.osha.gov/laws-regs/regulations/standardnumber/1926/1926.403
Independent practice; verify any reference hint against the edition and category permitted for your booking. Official exam and reference-list sources →
More NASCLA Questions
A contract permits payment for stored materials only with specified documentation. Which submission supports that payment review?
A tempered glass panel is 5 ft by 9 ft. The supplier weight is 6.5 lb per square foot. What is the panel weight before hardware?
The owner will buy major equipment directly, while the contractor remains responsible for coordination and installation. What must be clarified before the purchase is released?
Which minimum eccentric gravity load and distance does OSHA 1926.755(a)(2) specify for the column anchor-rod assembly during erection?
Using 1 refrigeration ton = 12,000 Btu/h, how many tons of cooling correspond to a scheduled capacity of 180,000 Btu/h?
On the supplied schematic practice drawing (S-741), what is the sum of the three printed chain dimensions? Use the dimension labels rather than scaling the sloping graphic.
Why are backfill lifts limited in thickness?
The specified resilient flooring and adhesive require slab moisture and pH checks before installation. Testing has not been completed, but the crew wants to meet turnover. What should happen?
The approved backfill procedure limits loose lifts to 8 inches for this soil and compactor. A crew places one 24-inch loose lift. What should be done?
Under 2021 IBC 1507.7.2, what is the minimum roof-deck slope for natural slate shingles?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
Project Management
60 questions · 70% to pass
Related Study Resources
Previous Question
A hydronic piping scope has 28 straight pipe pieces, each 20 ft long. The insulation order includes 5 percent for cuts and fittings. What insulation length should be carried?
Next Question
A long CMU corridor wall has no control joints shown near a re-entrant corner, and shrinkage cracking is likely to concentrate there. What is the best preconstruction action?