A hydronic piping scope has 28 straight pipe pieces, each 20 ft long. The insulation order includes 5 percent for cuts and fittings. What insulation length should be carried?
Correct Answer
A) 588 ft
Base length is 28 x 20 = 560 ft. Adding 5 percent gives 560 x 1.05 = 588 ft. Other choices omit waste, add only half the allowance, or round to a larger stock number.
Why This Is the Correct Answer
Base length is 28 x 20 = 560 ft. Adding 5 percent gives 560 x 1.05 = 588 ft. Other choices omit waste, add only half the allowance, or round to a larger stock number.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
A rooftop unit schedule lists capacity in tons of cooling. In HVAC estimating, one ton of cooling equals what heat-transfer rate?
The bid form asks for a base bid and three alternates. How should the contractor submit alternate pricing?
A specification includes a $40,000 hardware allowance because final selections are pending. How is the allowance treated in the bid?
The earthwork section requires unit prices for unsuitable-soil removal. What is the contract-administration use of those unit prices?
Before the first progress payment, the owner requests a schedule of values. What is its main contract-payment function?
A signed change order is issued for added lobby millwork. Which contract effect should it state?
On the finish plan, locate room R358; then use the finish schedule. What remarks is listed?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A supplier delivers material before the related submittal is approved. What should receiving personnel do?
Next Question
A custom pump is required on site by day 110. Review takes 14 days, fabrication takes 42 days, and shipping takes 6 days after release. What is the latest day the submittal can be issued for review?