A supplier delivers material before the related submittal is approved. What should receiving personnel do?
Correct Answer
D) Quarantine or hold the material until compliance and approval status are verified.
Early delivery does not prove contract compliance; receiving should verify approval and requirements.
Why This Is the Correct Answer
Early delivery does not prove contract compliance; receiving should verify approval and requirements.
Why the Other Options Are Wrong
Option A: Install it immediately because it arrived
In general project requirements, Install it immediately because it arrived. is the wrong selection for First delivery submittal check: it answers the First delivery submittal check prompt with the wrong practical move.
Option B: Assume the contractor may pay the supplier without review when applying first delivery submittal check
The trap in B is Pay the supplier without review. That selection is wrong because the action skips the timing, documentation, or field-control step needed for First delivery submittal check.
Option C: The project manager should remove the submittal requirement
Choice C gives Remove the submittal requirement. Its specific error: the choice would not get the project to Quarantine or hold the material until compliance and approval status are verified.
Memory Technique
Pair first delivery submittal check with the real field trigger, then choose the response that produces Quarantine or hold the material until compliance and approval status are verified.
Reference Hint
Open Construction Jobsite Management, 5th Ed. (2024); use by topic index - documentation / submittals / RFIs / closeout to confirm that Early delivery does not prove contract compliance; receiving should verify approval and requirements.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
The owner asks for a documented basis: how far from the excavation edge should spoil be kept unless retained?
Next Question
A hydronic piping scope has 28 straight pipe pieces, each 20 ft long. The insulation order includes 5 percent for cuts and fittings. What insulation length should be carried?