A long CMU corridor wall has no control joints shown near a re-entrant corner, and shrinkage cracking is likely to concentrate there. What is the best preconstruction action?
Correct Answer
C) Coordinate the control-joint layout with the designer before laying the affected wall
Raise the concern with the designer before construction and resolve the intended crack-control detail. Joint placement must work with reinforcement, wall function and expected movement. Do not cut reinforcement or replace structural mortar with caulk indiscriminately. Concrete masonry can undergo shrinkage; simply waiting for a crack is not a design resolution. Source: https://www.cmha.org/resource/cmu-tec-009/
Why This Is the Correct Answer
Raise the concern with the designer before construction and resolve the intended crack-control detail. Joint placement must work with reinforcement, wall function and expected movement. Do not cut reinforcement or replace structural mortar with caulk indiscriminately. Concrete masonry can undergo shrinkage; simply waiting for a crack is not a design resolution. Source: https://www.cmha.org/resource/cmu-tec-009/
Independent practice; verify any reference hint against the edition and category permitted for your booking. Official exam and reference-list sources →
More NASCLA Questions
A contract permits payment for stored materials only with specified documentation. Which submission supports that payment review?
A tempered glass panel is 5 ft by 9 ft. The supplier weight is 6.5 lb per square foot. What is the panel weight before hardware?
The owner will buy major equipment directly, while the contractor remains responsible for coordination and installation. What must be clarified before the purchase is released?
Which minimum eccentric gravity load and distance does OSHA 1926.755(a)(2) specify for the column anchor-rod assembly during erection?
Using 1 refrigeration ton = 12,000 Btu/h, how many tons of cooling correspond to a scheduled capacity of 180,000 Btu/h?
On the supplied schematic practice drawing (S-741), what is the sum of the three printed chain dimensions? Use the dimension labels rather than scaling the sloping graphic.
Why are backfill lifts limited in thickness?
The specified resilient flooring and adhesive require slab moisture and pH checks before installation. Testing has not been completed, but the crew wants to meet turnover. What should happen?
The approved backfill procedure limits loose lifts to 8 inches for this soil and compactor. A crew places one 24-inch loose lift. What should be done?
Under 2021 IBC 1507.7.2, what is the minimum roof-deck slope for natural slate shingles?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
Project Management
60 questions · 70% to pass
Related Study Resources
Previous Question
Stored ceiling tile pallets are placed directly in front of a switchgear lineup on the day of startup. What should the superintendent require before energization work proceeds?
Next Question
A subcontract expressly conditions payment certification for stored equipment on invoice, insurance and storage evidence. The subcontractor has provided none of it. How should that portion be reviewed?
