Bidder A includes a $22,000 allowance in its bid. Bidder B excludes that same required allowance and bids $1,318,000. What normalized comparison number should be used for Bidder B?
Correct Answer
A) $1,340,000
To compare equal scope, add the excluded required allowance to Bidder B: $1,318,000 + $22,000 = $1,340,000. Other choices subtract, leave the scope gap, or add the allowance twice.
Why This Is the Correct Answer
To compare equal scope, add the excluded required allowance to Bidder B: $1,318,000 + $22,000 = $1,340,000. Other choices subtract, leave the scope gap, or add the allowance twice.
Why the Other Options Are Wrong
Option B: $1,296,000
bid comparison normalization, choice a: $1,318,000 - $22,000 gives $1,296,000. That calculation subtracts those two listed numbers in that order.
Option C: $1,318,000
bid comparison normalization, choice b: the number $1,318,000 comes from $1,318,000 but stops before the calculation reaches $1,340,000.
Option D: $1,362,000
bid comparison normalization, choice d: $1,362,000 is off by $22,000 from the checked result $1,340,000 because it misuses the $22,000 item (Bidder A includes a $22,000 allowance in its bid).
Memory Technique
Store bid comparison normalization with its last math move; nearby answers are usually unfinished versions of $1,340,000.
Reference Hint
Open Construction Project Management, 5th Ed. (2022); use the index entry or section for "Bid leveling and allowance normalization" to confirm that To compare equal scope, add the excluded required allowance to Bidder B: $1,318,000 + $22,000 = $1,340,000.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A contract holds a $30,000 warranty reserve. After correction of accepted items, 80 percent of the reserve is released. What amount remains reserved?
Next Question
A crew is about to use a new solvent adhesive, but the safety data sheet is not available on site and workers have not been briefed on the hazards. What should happen first?