A contract holds a $30,000 warranty reserve. After correction of accepted items, 80 percent of the reserve is released. What amount remains reserved?
Correct Answer
B) $6,000
Released reserve is $30,000 x 80% = $24,000, so remaining reserve is $30,000 - $24,000 = $6,000. Other choices use 40%, report released amount, or leave the full reserve.
Why This Is the Correct Answer
Released reserve is $30,000 x 80% = $24,000, so remaining reserve is $30,000 - $24,000 = $6,000. Other choices use 40%, report released amount, or leave the full reserve.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
A rooftop unit schedule lists capacity in tons of cooling. In HVAC estimating, one ton of cooling equals what heat-transfer rate?
The bid form asks for a base bid and three alternates. How should the contractor submit alternate pricing?
A specification includes a $40,000 hardware allowance because final selections are pending. How is the allowance treated in the bid?
The earthwork section requires unit prices for unsuitable-soil removal. What is the contract-administration use of those unit prices?
Before the first progress payment, the owner requests a schedule of values. What is its main contract-payment function?
A signed change order is issued for added lobby millwork. Which contract effect should it state?
On the finish plan, locate room R358; then use the finish schedule. What remarks is listed?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A superintendent compares the field record with the contract: at what break in elevation must access be provided when no ramp or hoist is available?
Next Question
Bidder A includes a $22,000 allowance in its bid. Bidder B excludes that same required allowance and bids $1,318,000. What normalized comparison number should be used for Bidder B?