A contract holds a $30,000 warranty reserve. After correction of accepted items, 80 percent of the reserve is released. What amount remains reserved?
Correct Answer
B) $6,000
Released reserve is $30,000 x 80% = $24,000, so remaining reserve is $30,000 - $24,000 = $6,000. Other choices use 40%, report released amount, or leave the full reserve.
Why This Is the Correct Answer
Released reserve is $30,000 x 80% = $24,000, so remaining reserve is $30,000 - $24,000 = $6,000. Other choices use 40%, report released amount, or leave the full reserve.
Why the Other Options Are Wrong
Option A: $12,000
warranty reserve release, choice b: $12,000 backs into 15,000 when divided by 80 percent; the accepted setup gives 7,500 on that same base.
Option C: $24,000
warranty reserve release, choice c: the number $24,000 comes from $30,000 x 80 percent.
Option D: $30,000
warranty reserve release, choice d: $30,000 equals $30,000. That copies a listed value without completing the operation.
Memory Technique
Picture a rough-in sticker labeled warranty reserve release: finish every operation before accepting $6,000.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Warranty reserve release" to confirm that Released reserve is $30,000 x 80% = $24,000, so remaining reserve is $30,000 - $24,000 = $6,000.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A superintendent compares the field record with the contract: at what break in elevation must access be provided when no ramp or hoist is available?
Next Question
Bidder A includes a $22,000 allowance in its bid. Bidder B excludes that same required allowance and bids $1,318,000. What normalized comparison number should be used for Bidder B?
