A crew is about to use a new solvent adhesive, but the safety data sheet is not available on site and workers have not been briefed on the hazards. What should happen first?
Correct Answer
A) Obtain the SDS and communicate the hazards before the adhesive is used
Hazard communication requires workers to have access to hazard information before using chemical products. Other choices delay or avoid the information workers need to use the product safely.
Why This Is the Correct Answer
Hazard communication requires workers to have access to hazard information before using chemical products. Other choices delay or avoid the information workers need to use the product safely.
Why the Other Options Are Wrong
Option B: The crew should use the product if the container is unopened
In general project requirements, Use the product if the container is unopened is the wrong selection for Hazard communication: the option does not produce the required Hazard communication outcome, Obtain the SDS and communicate the hazards before the adhesive is used.
Option C: Rely on the supplier's website after the shift
The trap in C is Rely on the supplier's website after the shift. That selection is wrong because it points to Rely on the supplier's website after the shift, but.
Option D: Let only the fastest worker use it and use that item to close hazard communication
Choice D gives Let only the fastest worker use it. Its specific error: the action skips the timing, documentation, or field-control step needed for Hazard communication.
Memory Technique
Use the phrase "problem, control, result" for hazard communication; the result side is Obtain the SDS and communicate the hazards before the adhesive is used.
Reference Hint
Open 29 CFR 1926 OSHA Construction Standards; use 29 CFR 1926.59 / hazard communication principles to confirm that Hazard communication requires workers to have access to hazard information before using chemical products.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass