A drywall scope has 28 outside corners, each 9 ft high. Corner bead is ordered in 10 ft sticks with no splicing planned. What stick count is needed?
Correct Answer
C) 28 sticks
Each 9 ft corner needs one 10 ft stick when no splicing is planned. With 28 outside corners, the order is 28 sticks. Other choices divide total footage by stick length and ignore no-splice waste, or add extra allowance not stated.
Why This Is the Correct Answer
Each 9 ft corner needs one 10 ft stick when no splicing is planned. With 28 outside corners, the order is 28 sticks. Other choices divide total footage by stick length and ignore no-splice waste, or add extra allowance not stated.
Why the Other Options Are Wrong
Option A: 26 sticks
corner bead length, choice b: 26 sticks backs into 26 when divided by 28 / 28; the accepted setup gives 28 on that same base.
Option B: 31 sticks
corner bead length, choice c: 31 sticks backs into 31 when divided by 28 / 28; the accepted setup gives 28 on that same base.
Option D: 35 sticks
corner bead length, choice d: 35 sticks backs into 35 when divided by 28 / 28; the accepted setup gives 28 on that same base.
Memory Technique
Say the corner bead length rule aloud as a chain; the chain ends at 28 sticks, not an intermediate stop.
Reference Hint
Open Gypsum Construction Handbook, 7th Ed., 2014; use the index entry or section for "Gypsum board corner reinforcement takeoff" to confirm that Each 9 ft corner needs one 10 ft stick when no splicing is planned.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass