A framing detail conflicts between the plan and wall section. What is the proper use of an RFI in this situation?
Correct Answer
C) To request clarification of the contract documents before proceeding with affected work
An RFI requests clarification of contract documents so the contractor can proceed with the intended work. Other choices misuse an RFI as substitution approval, a scope shield, or an automatic time change.
Why This Is the Correct Answer
An RFI requests clarification of contract documents so the contractor can proceed with the intended work. Other choices misuse an RFI as substitution approval, a scope shield, or an automatic time change.
Why the Other Options Are Wrong
Option A: Close contract execution first and resolve the rFI purpose record later
Choice A gives To approve a substitute product without review. Its specific error: it tries to bypass the RFI purpose checkpoint.
Option B: Accept the price information as submitted and leave rFI purpose unverified
Choice B (To hide a known scope exclusion) is rejected because it leaves the work at an informal or incomplete stage, while RFI purpose requires To request clarification of the contract documents before proceeding with affected work.
Option D: Allow the work to continue until closeout review of rFI purpose
The trap in D is To change contract time automatically. That selection is wrong because it points to To change contract time automatically, but.
Memory Technique
Use a ledger line memory cue for RFI purpose: the stem's condition unlocks To request clarification of the contract documents before proceeding with affected work.
Reference Hint
Open Construction Jobsite Management, 5th Ed.; use the index entry or section for "Requests for information" to confirm that An RFI requests clarification of contract documents so the contractor can proceed with the intended work.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass