EstatePass
NASCLAContractsmedium27% of exam part

A framing detail conflicts between the plan and wall section. What is the proper use of an RFI in this situation?

Correct Answer

C) To request clarification of the contract documents before proceeding with affected work

An RFI requests clarification of contract documents so the contractor can proceed with the intended work. Other choices misuse an RFI as substitution approval, a scope shield, or an automatic time change.

Answer Options
A
Close contract execution first and resolve the rFI purpose record later
B
Accept the price information as submitted and leave rFI purpose unverified
C
To request clarification of the contract documents before proceeding with affected work
D
Allow the work to continue until closeout review of rFI purpose

Why This Is the Correct Answer

An RFI requests clarification of contract documents so the contractor can proceed with the intended work. Other choices misuse an RFI as substitution approval, a scope shield, or an automatic time change.

Why the Other Options Are Wrong

Option A: Close contract execution first and resolve the rFI purpose record later

Choice A gives To approve a substitute product without review. Its specific error: it tries to bypass the RFI purpose checkpoint.

Option B: Accept the price information as submitted and leave rFI purpose unverified

Choice B (To hide a known scope exclusion) is rejected because it leaves the work at an informal or incomplete stage, while RFI purpose requires To request clarification of the contract documents before proceeding with affected work.

Option D: Allow the work to continue until closeout review of rFI purpose

The trap in D is To change contract time automatically. That selection is wrong because it points to To change contract time automatically, but.

Memory Technique

Use a ledger line memory cue for RFI purpose: the stem's condition unlocks To request clarification of the contract documents before proceeding with affected work.

Reference Hint

Open Construction Jobsite Management, 5th Ed.; use the index entry or section for "Requests for information" to confirm that An RFI requests clarification of contract documents so the contractor can proceed with the intended work.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.