A fill area needs 2,040 compacted cubic yards. If shrinkage from loose to compacted volume is 15 percent, what loose volume is needed?
Correct Answer
C) 2,400 cy
Loose volume is 2,040 / 0.85 = 2,400 cy.
Why This Is the Correct Answer
Loose volume is 2,040 / 0.85 = 2,400 cy.
Why the Other Options Are Wrong
Option A: 2,160 cy
loose volume for compacted fill, choice b: 2,160 cy is wrong because 2,160 cy implies compacted volume is about 94.44 percent of loose volume; the accepted shrinkage factor is 85 percent in.
Option B: 2,640 cy
loose volume for compacted fill, choice c: 2,640 cy implies compacted volume is about 77.27 percent of loose volume; the accepted shrinkage factor is 85 percent in.
Option D: 1,734 cy
loose volume for compacted fill, choice d: 1,734 cy implies compacted volume is about 117.65 percent of loose volume; the accepted shrinkage factor is 85 percent in.
Memory Technique
Picture a panel space labeled loose volume for compacted fill: finish every operation before accepting 2,400 cy.
Reference Hint
Open Pipe and Excavation Contracting, 2011; use by topic index - earthwork volume / swell / shrink to confirm that Loose volume is 2,040 / 0.85 = 2,400 cy.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass