The structural drawings specify f'c but do not name a different test age. For standard-cured cylinders used to verify f'c, the default ACI test age is which one?
Correct Answer
B) 28 days
ACI 318 strength acceptance is based on the specified compressive strength at 28 days unless another test age is designated, so the default verification age is 28 days. Other choices: 7 days is often used for early information, 56 days can be specified for some mixtures, and 90 days is not the default f'c age.
Why This Is the Correct Answer
ACI 318 strength acceptance is based on the specified compressive strength at 28 days unless another test age is designated, so the default verification age is 28 days.
Why the Other Options Are Wrong
Option A: 7 days
In concrete work, 7 days is the wrong selection for Standard test age: 7 days is a different published number than the cited Standard test age value; ACI 318-19 Ch. 2 definition of f'c and 26.12 strength testing supports 28 days.
Option C: 56 days
Choice C gives 56 days. Its specific error: 56 days is a different published number than the cited Standard test age value; ACI 318-19 Ch. 2 definition of f'c and 26.12 strength testing supports 28 days. The accepted answer is 28 days.
Option D: 90 days
Choice D (90 days) is rejected because 90 days is a different published number than the cited Standard test age value; ACI 318-19 Ch. 2 definition of f'c and 26.12 strength testing supports 28 days. The cited answer is 28 days.
Memory Technique
Make standard test age a tabbed card: cite the exact condition, then choose 28 days.
Reference Hint
Open ACI 318-19, Building Code Requirements for Structural Concrete; use ACI 318-19 Ch. 2 definition of f'c and 26.12 strength testing to confirm that ACI 318 strength acceptance is based on the specified compressive strength at 28 days unless another test age is designated, so the default verification age is 28 days.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass