A condensate drain must slope 1/8 in. per ft for 64 ft. What total fall is required?
Correct Answer
A) 8 in.
Total fall is 64 ft x 1/8 in. per ft = 8 in.
Why This Is the Correct Answer
Total fall is 64 ft x 1/8 in. per ft = 8 in.
Why the Other Options Are Wrong
Option B: 4 in.
pipe slope fall, choice a: 4 in. is wrong because 4 in. implies about 6.25 percent fall over 64 ft; the stated slope is the one used in.
Option C: 6 in.
pipe slope fall, choice c: 6 in. implies about 9.38 percent fall over 64 ft; the stated slope is the one used in.
Option D: 12 in.
pipe slope fall, choice d: 12 in. is wrong because 12 in. implies about 18.75 percent fall over 64 ft; the stated slope is the one used in.
Memory Technique
Keep a anchor beside pipe slope fall: if one number is skipped, the option drifts away from 8 in.
Reference Hint
Open Mechanical and Electrical Systems for Construction Managers, 4th Ed., 2024; use by topic index - M/P fallback to confirm that Total fall is 64 ft x 1/8 in.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
