A subcontractor disagrees with an assigned action item in draft meeting minutes. What should the contractor do?
Correct Answer
C) Resolve the comment promptly and issue corrected or confirmed minutes.
Meeting minutes should be corrected or confirmed so the project record is reliable.
Why This Is the Correct Answer
Meeting minutes should be corrected or confirmed so the project record is reliable.
Why the Other Options Are Wrong
Option A: The contractor should ignore the comment permanently
Choice A (Ignore the comment permanently.) is rejected because it tries to bypass the Meeting minutes dispute checkpoint.
Option B: The contractor should delete all action items
In general project requirements, Delete all action items. is the wrong selection for Meeting minutes dispute: it removes the controlling Meeting minutes dispute requirement instead of meeting it.
Option D: Convert the minutes into a change order, leaving meeting minutes dispute unverified
Choice D gives Convert the minutes into a change order. Its specific error: the option answers a paperwork, payment, or bonding issue.
Memory Technique
Tag the scene with meeting minutes dispute: wrong actor or wrong timing means the fix is not Resolve the comment promptly and issue corrected or confirmed minutes.
Reference Hint
Open Construction Jobsite Management, 5th Ed. (2024); use by topic index - documentation / submittals / RFIs / closeout to confirm that Meeting minutes should be corrected or confirmed so the project record is reliable.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass