A perimeter column is being fabricated for a multistory steel frame. How far must it normally extend above the finished floor so perimeter safety cables can be installed before the next tier?
Correct Answer
D) 48 in.
OSHA 1926.756(e)(1) requires perimeter columns to extend a minimum of 48 in. above the finished floor to permit perimeter safety cables before erection of the next tier, except where constructibility does not allow. Other choices do not match the stated minimum.
Why This Is the Correct Answer
OSHA 1926.756(e)(1) requires perimeter columns to extend a minimum of 48 in. above the finished floor to permit perimeter safety cables before erection of the next tier, except where constructibility does not allow. Other choices do not match the stated minimum.
Why the Other Options Are Wrong
Option A: 24 in.
In metals work, 24 in. is the wrong selection for Perimeter columns: 24 in. is a different published number than the cited Perimeter columns value; 29 CFR 1926.756(e)(1) supports 48 in.
Option B: 30 in.
The trap in B is 30 in. That selection is wrong because 30 in. is a different published number than the cited Perimeter columns value; 29 CFR 1926.756(e)(1) supports 48 in.; Perimeter columns normally extend at least 48 in. above the finished floor.
Option C: 36 in.
Choice C gives 36 in. Its specific error: 36 in. is a different published number than the cited Perimeter columns value; 29 CFR 1926.756(e)(1) supports 48 in. The accepted answer is 48 in.
Memory Technique
Use a checkpoint memory cue for perimeter columns: the stem's condition unlocks 48 in.
Reference Hint
Open 29 CFR Part 1926, Subpart R - Steel Erection; use 29 CFR 1926.756(e)(1) to confirm that OSHA 1926.756(e)(1) requires perimeter columns to extend a minimum of 48 in.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass