Before the first progress payment, the owner requests a schedule of values. What is its main contract-payment function?
Correct Answer
A) Allocate the contract sum among work items as the basis for reviewing progress payments
The schedule of values allocates the contract amount across work items and supports review of pay applications. Other choices confuse it with schedule management, contacts, or product review.
Why This Is the Correct Answer
The schedule of values allocates the contract amount across work items and supports review of pay applications. Other choices confuse it with schedule management, contacts, or product review.
Why the Other Options Are Wrong
Option B: The owner should replace the construction schedule as though it satisfied the specific schedule of values requirement
In procurement and contracting, Replace the construction schedule is the wrong selection for Schedule of values: it removes the controlling Schedule of values requirement instead of meeting it.
Option C: Use a later change request to handle schedule of values after award
The trap in C is List only subcontractor phone numbers. That selection is wrong because the option delays or omits the controlling step.
Option D: The owner should approve substitutions without architect review
Choice D gives Approve substitutions without architect review. Its specific error: the action skips the timing, documentation, or field-control step needed for Schedule of values.
Memory Technique
File schedule of values under a anchor: condition first, number or duty second, answer Allocate the contract sum among work items as the basis for reviewing progress payments.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Schedule of values and progress payments" to confirm that The schedule of values allocates the contract amount across work items and supports review of pay applications.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass