A rectangular lite is 42 in. wide and 78 in. high. Glazing stop is needed around all four sides, and the cut list adds 10 percent waste. What stop length should be carried?
Correct Answer
D) 264 in.
Perimeter is 2 x (42 + 78) = 240 in. Adding 10 percent waste gives 240 x 1.10 = 264 in. Other choices omit one side, omit waste, or add too much allowance.
Why This Is the Correct Answer
Perimeter is 2 x (42 + 78) = 240 in. Adding 10 percent waste gives 240 x 1.10 = 264 in. Other choices omit one side, omit waste, or add too much allowance.
Why the Other Options Are Wrong
Option A: 220 in.
glazing stops, choice a: 220 in. implies about -8.33 percent added to 240; the stated add-on is 10 percent in.
Option B: 240 in.
glazing stops, choice b: 240 in. is an intermediate from the steps (Perimeter is 2 x (42 + 78) = 240 in.); the calculation continues to 264 in.
Option C: 280 in.
glazing stops, choice d: 280 in. implies about 16.67 percent added to 240; the stated add-on is 10 percent in.
Memory Technique
Store glazing stops with its last math move; nearby answers are usually unfinished versions of 264 in.
Reference Hint
Open Principles and Practices of Commercial Construction, 11th Ed., 2024; use the index entry or section for "Glazing stop cut length takeoff" to confirm that Perimeter is 2 x (42 + 78) = 240 in.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
After bids are evaluated, the owner sends the selected bidder a written notice that it has been chosen for the contract subject to furnishing required documents. Which procurement document is this?
Next Question
A major structural addendum is issued a few hours before bids are due, and several bidders cannot obtain subcontractor pricing. What procurement action best protects fair competition?
