A rectangular lite is 42 in. wide and 78 in. high. Glazing stop is needed around all four sides, and the cut list adds 10 percent waste. What stop length should be carried?
Correct Answer
D) 264 in.
Perimeter is 2 x (42 + 78) = 240 in. Adding 10 percent waste gives 240 x 1.10 = 264 in. Other choices omit one side, omit waste, or add too much allowance.
Why This Is the Correct Answer
Perimeter is 2 x (42 + 78) = 240 in. Adding 10 percent waste gives 240 x 1.10 = 264 in. Other choices omit one side, omit waste, or add too much allowance.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
A rooftop unit schedule lists capacity in tons of cooling. In HVAC estimating, one ton of cooling equals what heat-transfer rate?
The bid form asks for a base bid and three alternates. How should the contractor submit alternate pricing?
A specification includes a $40,000 hardware allowance because final selections are pending. How is the allowance treated in the bid?
The earthwork section requires unit prices for unsuitable-soil removal. What is the contract-administration use of those unit prices?
Before the first progress payment, the owner requests a schedule of values. What is its main contract-payment function?
A signed change order is issued for added lobby millwork. Which contract effect should it state?
On the finish plan, locate room R358; then use the finish schedule. What remarks is listed?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
After bids are evaluated, the owner sends the selected bidder a written notice that it has been chosen for the contract subject to furnishing required documents. Which procurement document is this?
Next Question
A major structural addendum is issued a few hours before bids are due, and several bidders cannot obtain subcontractor pricing. What procurement action best protects fair competition?