A critical equipment submittal is two weeks late and fabrication cannot start. What should be escalated?
Correct Answer
C) Submittal status, decision owner, recovery options, and schedule impact.
Long-lead delays need prompt escalation because review and fabrication control delivery.
Why This Is the Correct Answer
Long-lead delays need prompt escalation because review and fabrication control delivery.
Why the Other Options Are Wrong
Option A: Limit long-lead submittal delay to the color of the cover sheet
Choice A (Only the color of the cover sheet.) is rejected because the action skips the timing, documentation, or field-control step needed for Long-lead submittal delay.
Option B: Base the long-lead submittal delay response on the warranty start date only
In general project requirements, Only the warranty start date. is the wrong selection for Long-lead submittal delay: it tries to bypass the Long-lead submittal delay checkpoint.
Option D: Treat the condition as requiring no action until delivery day
Choice D gives No action until delivery day. Its specific error: the option does not produce the required Long-lead submittal delay outcome, Submittal status, decision owner, recovery options, and schedule impact.
Memory Technique
Use the phrase "problem, control, result" for long-lead submittal delay; the result side is Submittal status, decision owner, recovery options, and schedule impact.
Reference Hint
Open Construction Jobsite Management, 5th Ed. (2024); use by topic index - documentation / submittals / RFIs / closeout to confirm that Long-lead delays need prompt escalation because review and fabrication control delivery.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A major structural addendum is issued a few hours before bids are due, and several bidders cannot obtain subcontractor pricing. What procurement action best protects fair competition?
Next Question
For the owner coordination call, a unit-price item overruns by 329 cy at $117/cy. What added payment is due?