Mortar on a board has started to stiffen late in the morning. The mason asks to add water repeatedly and keep it for the afternoon. What should the foreman require?
Correct Answer
B) Follow the specification limits for retempering and discard mortar that has begun to set or exceeded its allowed time
Mortar can only be retempered within allowed limits before initial set or the specified time limit; old or setting mortar should be discarded. Other choices weaken quality control or hide poor mortar in selected joints.
Why This Is the Correct Answer
Mortar can only be retempered within allowed limits before initial set or the specified time limit; old or setting mortar should be discarded. Other choices weaken quality control or hide poor mortar in selected joints.
Why the Other Options Are Wrong
Option A: The foreman should keep retempering indefinitely as long as color is unchanged
Choice A gives Keep retempering indefinitely as long as color is unchanged. Its specific error: it points to Keep retempering indefinitely as long as color is unchanged, but.
Option C: Add hydrated lime until the mortar softens
In masonry work, Add hydrated lime until the mortar softens is the wrong selection for Mortar retempering: it leaves out the controlling Mortar retempering result: Follow the specification limits for retempering and discard mortar that has begun to set or exceeded its.
Option D: The foreman should use the old mortar only for head joints
The trap in D is Use the old mortar only for head joints. That selection is wrong because it leaves the work at an informal or incomplete stage, while Mortar retempering requires Follow the specification limits for retempering and discard mortar that has begun to set or.; Mortar retempering is limited; mortar that has begun to set or is too old should not be used.
Memory Technique
Pair mortar retempering with the real field trigger, then choose the response that produces Follow the specification limits for retempering and discard mortar that has begun to set or exceeded its allowed time.
Reference Hint
Open Modern Masonry - Brick, Block, Stone, 9th Ed., 2020; use the index entry or section for "Mortar mixing, tempering, and time limits" to confirm that Mortar can only be retempered within allowed limits before initial set or the specified time limit; old or setting mortar should be discarded.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass