A CPM activity’s early start is the beginning of working day 52 and its late start is the beginning of working day 101 on the same calendar. What total float is shown?

Correct Answer

A) 49 days

Total float = late start − early start =101−52=49 working days on the stated calendar. The result is not a claims-notice deadline or proof that all 49 days belong exclusively to this activity. Source: https://www.gao.gov/assets/gao-16-89g.pdf

Answer Options
A
49 days
B
48 days
C
50 days
D
52 days

Why This Is the Correct Answer

Total float = late start − early start =101−52=49 working days on the stated calendar. The result is not a claims-notice deadline or proof that all 49 days belong exclusively to this activity. Source: https://www.gao.gov/assets/gao-16-89g.pdf

Independent practice; verify any reference hint against the edition and category permitted for your booking. Official exam and reference-list sources →

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.