A crew works 20 overtime hours with a $36/hr base rate and time-and-one-half premium. What is the overtime labor cost?
Correct Answer
C) $1,080
The overtime rate is $36 x 1.5 = $54/hr, and 20 x $54 = $1,080.
Why This Is the Correct Answer
The overtime rate is $36 x 1.5 = $54/hr, and 20 x $54 = $1,080.
Why the Other Options Are Wrong
Option A: $720
overtime premium cost, choice a: $720 is produced by 20 x $36. The error is using that partial/alternate setup.
Option B: $900
overtime premium cost, choice c: $900 backs into 25 when divided by $36; the accepted setup gives 30 on that same base.
Option D: $1,440
overtime premium cost, choice d: $1,440 backs into 40 when divided by $36; the accepted setup gives 30 on that same base.
Memory Technique
Store overtime premium cost with its last math move; nearby answers are usually unfinished versions of $1,080.
Reference Hint
Open Construction Jobsite Management, 5th Ed. (2024); use by topic index - labor hours / productivity / earned value / job cost to confirm that The overtime rate is $36 x 1.5 = $54/hr, and 20 x $54 = $1,080.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study