An activity has an early start of day 14 and a late start of day 18. What total float is indicated by those dates?
Correct Answer
D) 4 days
Total float can be read as late start minus early start: 18 - 14 = 4 days. Other choices subtract the wrong dates or add the dates.
Why This Is the Correct Answer
Total float can be read as late start minus early start: 18 - 14 = 4 days. Other choices subtract the wrong dates or add the dates.
Why the Other Options Are Wrong
Option A: 2 days
total float, choice a: 2 days uses the wrong side of the schedule subtraction or omits one duration component.
Option B: 3 days
total float, choice b: 3 days is wrong because 3 days uses the wrong side of the schedule subtraction or omits one duration component.
Option C: 32 days
total float, choice d: 32 days uses the wrong side of the schedule subtraction or omits one duration component.
Memory Technique
Picture a fastener row labeled total float: finish every operation before accepting 4 days.
Reference Hint
Open Construction Jobsite Management, 5th Ed.; use the index entry or section for "Critical-path scheduling" to confirm that Total float can be read as late start minus early start: 18 - 14 = 4 days.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
An exterior air-entrained paving mix arrives below the specified slump after a long haul. The driver offers to add water at the chute until the crew likes the look. Which response is appropriate?
Next Question
Unauthorized visitors enter the site after hours. What project control should be strengthened?