An exterior air-entrained paving mix arrives below the specified slump after a long haul. The driver offers to add water at the chute until the crew likes the look. Which response is appropriate?
Correct Answer
C) Follow the approved adjustment procedure, retest slump and air, and reject the load if it cannot meet specification
Water added outside the approved procedure can raise water-cement ratio and disturb air content; the load needs controlled adjustment and retesting or rejection. Other choices: visual judgment, untested water addition, and bucket cement changes are not quality-controlled concrete practice.
Why This Is the Correct Answer
Water added outside the approved procedure can raise water-cement ratio and disturb air content; the load needs controlled adjustment and retesting or rejection.
Why the Other Options Are Wrong
Option A: The crew should accept the driver's judgment and place the load
The trap in A is Accept the driver's judgment and place the load. That selection is wrong because it leaves out the controlling Slump adjustment result: Follow the approved adjustment procedure, retest slump and air, and reject the load if it cannot meet.
Option B: Add water until finishing becomes easy, then skip testing
Choice B gives Add water until finishing becomes easy, then skip testing. Its specific error: the action skips the timing, documentation, or field-control step needed for Slump adjustment.
Option D: Add extra water and extra cement in equal buckets
In concrete work, Add extra water and extra cement in equal buckets is the wrong selection for Slump adjustment: it points to Add extra water and extra cement in equal buckets, but.
Memory Technique
Picture a tab on the jobsite; slump adjustment is solved by the action that leads to Follow the approved adjustment procedure, retest slump and air, and reject the load if it cannot meet specification.
Reference Hint
Open The Contractor's Guide to Quality Concrete Construction, 4th Ed., 2018; use the index entry or section for "Jobsite slump and air-content control" to confirm that Water added outside the approved procedure can raise water-cement ratio and disturb air content; the load needs controlled adjustment and retesting or rejection.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
