The owner needs a scope change to proceed before price and time are fully agreed. Which instrument is used to direct the change while reserving later adjustment?

Correct Answer

B) Construction change directive

A construction change directive directs a change before the parties have final agreement on price or time. Other choices are closeout, bidding, or payment documents rather than a directive to proceed with changed work.

Answer Options
A
Final lien waiver
B
Construction change directive
C
Certificate of substantial completion
D
Bid addendum

Why This Is the Correct Answer

A construction change directive directs a change before the parties have final agreement on price or time. Other choices are closeout, bidding, or payment documents rather than a directive to proceed with changed work.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.