The owner needs a scope change to proceed before price and time are fully agreed. Which instrument is used to direct the change while reserving later adjustment?
Correct Answer
B) Construction change directive
A construction change directive directs a change before the parties have final agreement on price or time. Other choices are closeout, bidding, or payment documents rather than a directive to proceed with changed work.
Why This Is the Correct Answer
A construction change directive directs a change before the parties have final agreement on price or time. Other choices are closeout, bidding, or payment documents rather than a directive to proceed with changed work.
Why the Other Options Are Wrong
Option A: Final lien waiver
The trap in A is Final lien waiver. That selection is wrong because it treats Construction change directive as optional.
Option C: Certificate of substantial completion
Choice C (Certificate of substantial completion) is rejected because it leaves out the controlling Construction change directive result: Construction change directive.
Option D: Bid addendum
In procurement and contracting, Bid addendum is the wrong selection for Construction change directive: it names a financial document or payment mechanism, not the Construction change directive action/result stated by Construction change directive.
Memory Technique
Link construction change directive to its book condition; a different condition means a different answer than Construction change directive.
Reference Hint
Open Construction Project Management, 5th Ed. (2022); use the index entry or section for "Construction change directive" to confirm that A construction change directive directs a change before the parties have final agreement on price or time.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A ceiling is being closed before the HVAC contractor has balanced branch airflows, and several balancing dampers will be inaccessible. What should be done?
Next Question
A delivery delay appears likely to affect a milestone, and the contract requires written notice within a stated period after the delaying event. What should the project manager do?