A delivery delay appears likely to affect a milestone, and the contract requires written notice within a stated period after the delaying event. What should the project manager do?
Correct Answer
B) Submit the required notice and supporting schedule information within the contract period
Delay or time-extension rights often depend on timely written notice and supporting schedule information. Other choices risk waiver or ignore the contract process.
Why This Is the Correct Answer
Delay or time-extension rights often depend on timely written notice and supporting schedule information. Other choices risk waiver or ignore the contract process.
Why the Other Options Are Wrong
Option A: The contractor should wait until final payment to mention the delay
Choice A gives Wait until final payment to mention the delay. Its specific error: the option delays or omits the controlling step.
Option C: Assume any delay automatically extends the contract
In procurement and contracting, Assume any delay automatically extends the contract is the wrong selection for Time extension notice: it answers the Time extension notice prompt with the wrong practical move.
Option D: The contractor should remove the milestone from the schedule without notice
The trap in D is Remove the milestone from the schedule without notice. That selection is wrong because it leaves the work at an informal or incomplete stage, while Time extension notice requires Submit the required.
Memory Technique
Remember time extension notice by its jobsite consequence: the correct move points to Submit the required notice and supporting schedule information within the contract period.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management - Basic, 14th Ed.; use by topic index - liquidated damages / delay / claim notice to confirm that Delay or time-extension rights often depend on timely written notice and supporting schedule information.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
The owner needs a scope change to proceed before price and time are fully agreed. Which instrument is used to direct the change while reserving later adjustment?
Next Question
A subcontractor is asked to sign a final unconditional lien waiver before receiving the final payment check. What document better matches payment that has not cleared yet?
