EstatePass
NASCLAContractsmedium27% of exam part

A subcontractor is asked to sign a final unconditional lien waiver before receiving the final payment check. What document better matches payment that has not cleared yet?

Correct Answer

B) Conditional waiver or release tied to actual receipt of payment

If payment has not been received or cleared, a conditional waiver tied to payment receipt better matches the transaction. Other choices are bidding, bonding, or submittal documents.

Answer Options
A
Classify the condition as a new bid addendum
B
Conditional waiver or release tied to actual receipt of payment
C
Base the conditional lien waiver response on a performance bond rider only
D
Classify the condition as a shop drawing stamp

Why This Is the Correct Answer

If payment has not been received or cleared, a conditional waiver tied to payment receipt better matches the transaction. Other choices are bidding, bonding, or submittal documents.

Why the Other Options Are Wrong

Option A: Classify the condition as a new bid addendum

Choice A gives A new bid addendum. Its specific error: it names a financial document or payment mechanism, not the Conditional lien waiver action/result stated by Conditional waiver or release tied to actual receipt of payment.

Option C: Base the conditional lien waiver response on a performance bond rider only

In procurement and contracting, A performance bond rider only is the wrong selection for Conditional lien waiver: it leaves the work at an informal or incomplete stage, while Conditional lien waiver requires Conditional waiver or release tied to actual receipt of payment.

Option D: Classify the condition as a shop drawing stamp

The trap in D is A shop drawing stamp. That selection is wrong because it points to A shop drawing stamp, but.

Memory Technique

Tag the scene with conditional lien waiver: wrong actor or wrong timing means the fix is not Conditional waiver or release tied to actual receipt of payment.

Reference Hint

Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Lien waiver and payment release practice" to confirm that If payment has not been received or cleared, a conditional waiver tied to payment receipt better matches the transaction.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.