A subcontractor is asked to sign a final unconditional lien waiver before receiving the final payment check. What document better matches payment that has not cleared yet?
Correct Answer
B) Conditional waiver or release tied to actual receipt of payment
If payment has not been received or cleared, a conditional waiver tied to payment receipt better matches the transaction. Other choices are bidding, bonding, or submittal documents.
Why This Is the Correct Answer
If payment has not been received or cleared, a conditional waiver tied to payment receipt better matches the transaction. Other choices are bidding, bonding, or submittal documents.
Why the Other Options Are Wrong
Option A: Classify the condition as a new bid addendum
Choice A gives A new bid addendum. Its specific error: it names a financial document or payment mechanism, not the Conditional lien waiver action/result stated by Conditional waiver or release tied to actual receipt of payment.
Option C: Base the conditional lien waiver response on a performance bond rider only
In procurement and contracting, A performance bond rider only is the wrong selection for Conditional lien waiver: it leaves the work at an informal or incomplete stage, while Conditional lien waiver requires Conditional waiver or release tied to actual receipt of payment.
Option D: Classify the condition as a shop drawing stamp
The trap in D is A shop drawing stamp. That selection is wrong because it points to A shop drawing stamp, but.
Memory Technique
Tag the scene with conditional lien waiver: wrong actor or wrong timing means the fix is not Conditional waiver or release tied to actual receipt of payment.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Lien waiver and payment release practice" to confirm that If payment has not been received or cleared, a conditional waiver tied to payment receipt better matches the transaction.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A delivery delay appears likely to affect a milestone, and the contract requires written notice within a stated period after the delaying event. What should the project manager do?
Next Question
A straight 32 ft partition has studs at 16 in. on center, with a stud at each end and no openings. What stud count should be carried for the run?