A straight 32 ft partition has studs at 16 in. on center, with a stud at each end and no openings. What stud count should be carried for the run?
Correct Answer
C) 25 studs
The run is 32 x 12 = 384 in. At 16 in. spacing, 384/16 = 24 spaces; with studs at both ends, count spaces plus one, so 25 studs. Other choices omit an end stud, add an extra bay, or use a shorter spacing.
Why This Is the Correct Answer
The run is 32 x 12 = 384 in. At 16 in. spacing, 384/16 = 24 spaces; with studs at both ends, count spaces plus one, so 25 studs. Other choices omit an end stud, add an extra bay, or use a shorter spacing.
Why the Other Options Are Wrong
Option A: 24 studs
stud layout, choice a: the answer choice lifts 24 studs from the working line spacing, 384/16 = 24 spaces.
Option B: 26 studs
stud layout, choice c: 26 studs is wrong because 26 studs adds one stud beyond the two-end layout; 84 spaces plus the far-end stud gives 85, not 86.
Option D: 28 studs
stud layout, choice d: 28 studs assumes a spacing/count different from 12 in. on center with studs at both ends; the accepted count is 84 spaces + 1 end stud = 85.
Memory Technique
Keep a panel space beside stud layout: if one number is skipped, the option drifts away from 25 studs.
Reference Hint
Open Carpentry and Building Construction, 2016; use the index entry or section for "Wall framing layout at regular stud spacing" to confirm that The run is 32 x 12 = 384 in.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A subcontractor is asked to sign a final unconditional lien waiver before receiving the final payment check. What document better matches payment that has not cleared yet?
Next Question
Gypsum board is being screw-attached to wood studs on a wall, away from panel edges. What maximum field screw spacing is commonly used for wall panels?
