A crane is holding a solid-web beam while ironworkers install the end connections. Before the hoisting line is released, what minimum OSHA connection condition must be met?
Correct Answer
B) At least two bolts per connection, drawn up wrench-tight or equivalent
OSHA 1926.756(a)(1) requires solid web structural members to be secured with at least two bolts per connection, of the same size and strength shown in the erection drawings, drawn up wrench-tight or equivalent before the hoisting line is released. Other choices are too little or require final work beyond the release minimum.
Why This Is the Correct Answer
OSHA 1926.756(a)(1) requires solid web structural members to be secured with at least two bolts per connection, of the same size and strength shown in the erection drawings, drawn up wrench-tight or equivalent before the hoisting line is released. Other choices are too little or require final work beyond the release minimum.
Why the Other Options Are Wrong
Option A: Base the solid web member release response on one started bolt at one end only
Choice A gives One started bolt at one end only. Its specific error: the action skips the timing, documentation, or field-control step needed for Solid web member release.
Option C: All final bolts fully tensioned and inspected, leaving solid web member release unverified
In metals work, All final bolts fully tensioned and inspected is the wrong selection for Solid web member release: it answers the Solid web member release prompt with the wrong practical move.
Option D: Base the solid web member release response on a tack weld at the top flange
The trap in D is A tack weld at the top flange only. That selection is wrong because the option delays or omits the controlling step.
Memory Technique
Make solid web member release a tabbed card: cite the exact condition, then choose At least two bolts per connection, drawn up wrench-tight or equivalent.
Reference Hint
Open 29 CFR Part 1926, Subpart R - Steel Erection; use 29 CFR 1926.756(a)(1) to confirm that OSHA 1926.756(a)(1) requires solid web structural members to be secured with at least two bolts per connection, of the same size and strength shown in the erection drawings, drawn up wrench-tight or equivalent before...
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass