Why might a design require selective coordination between an upstream feeder breaker and a downstream branch breaker?
Correct Answer
D) To have the downstream device clear a fault without unnecessarily opening upstream equipment
Selective coordination arranges protective devices so the device nearest the fault clears it when possible, limiting unnecessary outage area. Other choices invert the purpose or confuse coordination with unrelated equipment ratings.
Why This Is the Correct Answer
Selective coordination arranges protective devices so the device nearest the fault clears it when possible, limiting unnecessary outage area. Other choices invert the purpose or confuse coordination with unrelated equipment ratings.
Why the Other Options Are Wrong
Option A: Use selective coordination to make both breakers trip together so the fault is visibly cleared at every panel
In electrical work, To make both breakers trip for every small branch fault is the wrong selection for Selective coordination: the choice would not get the project to To have the downstream device clear a fault without unnecessarily opening upstream equipment, which is the Selective coordination result verified by the source.
Option B: Use selective coordination to eliminate the need for short-circuit ratings
The trap in B is To eliminate the need for short-circuit ratings. That selection is wrong because it removes the controlling Selective coordination requirement instead of meeting it.
Option C: Use selective coordination to make conductor insulation thinner
Choice C gives To make conductor insulation thinner. Its specific error: it points to To make conductor insulation thinner, but.
Memory Technique
Picture selective coordination doing the job; the answer names that job as To have the downstream device clear a fault without unnecessarily opening upstream equipment.
Reference Hint
Open Mechanical and Electrical Systems for Construction Managers, 4th Ed., 2024; use the index entry or section for "Electrical protection coordination" to confirm that Selective coordination arranges protective devices so the device nearest the fault clears it when possible, limiting unnecessary outage area.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass