The contract allows partial release of retainage after substantial completion of a phase. Which document controls whether that retainage can be released?
Correct Answer
B) The contract's retainage and closeout provisions
Retainage release depends on the contract provisions and required closeout conditions for the relevant work. Other choices do not control payment release.
Why This Is the Correct Answer
Retainage release depends on the contract provisions and required closeout conditions for the relevant work. Other choices do not control payment release.
Why the Other Options Are Wrong
Option A: Make the subcontractor's advertisement the answer for retainage release
In procurement and contracting, The subcontractor's advertisement is the wrong selection for Retainage release: the choice would not get the project to The contract's retainage and closeout provisions, which is the Retainage release result verified by the source.
Option C: Classify the condition as a deleted bid alternate
Choice C gives A deleted bid alternate. Its specific error: it treats Retainage release as optional.
Option D: Classify the condition as an unsigned daily report
Choice D (An unsigned daily report) is rejected because it answers the Retainage release prompt with the wrong practical move.
Memory Technique
Use a badge memory cue for retainage release: the stem's condition unlocks The contract's retainage and closeout provisions.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Retainage release conditions" to confirm that Retainage release depends on the contract provisions and required closeout conditions for the relevant work.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass