A signed change order is issued for added lobby millwork. Which contract effect should it state?

Correct Answer

D) The agreed change in work, contract sum, and contract time as applicable

A change order documents the agreed change in scope and any adjustment to contract sum and contract time. Other choices leave out core contract effects or substitute field records for a contract modification.

Answer Options
A
Base the change order response on the subcontractor's labor rate
B
Base the change order response on a drawing revision number only
C
Limit change order to the superintendent's daily report only
D
The agreed change in work, contract sum, and contract time as applicable

Why This Is the Correct Answer

A change order documents the agreed change in scope and any adjustment to contract sum and contract time. Other choices leave out core contract effects or substitute field records for a contract modification.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.