A signed change order is issued for added lobby millwork. Which contract effect should it state?
Correct Answer
D) The agreed change in work, contract sum, and contract time as applicable
A change order documents the agreed change in scope and any adjustment to contract sum and contract time. Other choices leave out core contract effects or substitute field records for a contract modification.
Why This Is the Correct Answer
A change order documents the agreed change in scope and any adjustment to contract sum and contract time. Other choices leave out core contract effects or substitute field records for a contract modification.
Why the Other Options Are Wrong
Option A: Base the change order response on the subcontractor's labor rate
In procurement and contracting, Only the subcontractor's labor rate is the wrong selection for Change order: it leaves the work at an informal or incomplete stage, while Change order requires The agreed change in work, contract sum, and contract time as applicable.
Option B: Base the change order response on a drawing revision number only
The trap in B is Only a drawing revision number. That selection is wrong because the option delays or omits the controlling step.
Option C: Limit change order to the superintendent's daily report only
Choice C gives Only the superintendent's daily report. Its specific error: the action skips the timing, documentation, or field-control step needed for Change order.
Memory Technique
Make change order a tabbed card: cite the exact condition, then choose The agreed change in work, contract sum, and contract time as applicable.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management - Basic, 14th Ed.; use by topic index - change orders to confirm that A change order documents the agreed change in scope and any adjustment to contract sum and contract time.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass