A flushing plan includes 300 ft of pipe with a 2 in. inside diameter. Using 7.48 gal/cf, what water volume is inside the pipe?
Correct Answer
B) 49.0 gal
Radius is 1 in. = 1/12 ft. Volume is pi x (1/12)^2 x 300 = 6.545 cf. Gallons are 6.545 x 7.48 = 49.0 gal. Other choices use the wrong radius, confuse diameter with radius, or skip the gallon conversion.
Why This Is the Correct Answer
Radius is 1 in. = 1/12 ft. Volume is pi x (1/12)^2 x 300 = 6.545 cf. Gallons are 6.545 x 7.48 = 49.0 gal.
Why the Other Options Are Wrong
Option A: 39.2 gal
pipe volume, choice b: 39.2 gal is wrong because 39.2 gal reflects a different quantity stage than the final takeoff.
Option C: 58.8 gal
pipe volume, choice c: 58.8 gal reflects a different quantity stage than the final takeoff.
Option D: 78.5 gal
pipe volume, choice d: 78.5 gal reflects a different quantity stage than the final takeoff.
Memory Technique
Picture a cover note labeled pipe volume: finish every operation before accepting 49.0 gal.
Reference Hint
Open Pipe and Excavation Contracting, 2011; use the index entry or section for "Pipe volume calculation" to confirm that Radius is 1 in.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?