Steel erection work is moving several levels above the last completed floor. How close must a fully planked or decked floor or nets be maintained directly under the erection work?
Correct Answer
A) Within two stories or 30 ft, whichever is less
OSHA 1926.754(b)(3) requires a fully planked or decked floor or nets within two stories or 30 ft, whichever is less, directly under erection work being performed. Other choices use other limits or omit the under-work requirement.
Why This Is the Correct Answer
OSHA 1926.754(b)(3) requires a fully planked or decked floor or nets within two stories or 30 ft, whichever is less, directly under erection work being performed. Other choices use other limits or omit the under-work requirement.
Why the Other Options Are Wrong
Option B: Within four stories or 48 ft, whichever is less
Choice B (Within four stories or 48 ft, whichever is less) is rejected because Within four stories or 48 ft, whichever is less is a different published number than the cited Decked floor or nets value; 29 CFR 1926.754(b)(3) supports W.
Option C: Within eight stories
In metals work, Within eight stories is the wrong selection for Decked floor or nets: it answers the Decked floor or nets prompt with the wrong practical move.
Option D: Only at grade level
The trap in D is Only at grade level. That selection is wrong because it tries to bypass the Decked floor or nets checkpoint.
Memory Technique
File decked floor or nets under a switch: condition first, number or duty second, answer Within two stories or 30 ft, whichever is less.
Reference Hint
Open 29 CFR Part 1926, Subpart R - Steel Erection; use 29 CFR 1926.754(b)(3) to confirm that OSHA 1926.754(b)(3) requires a fully planked or decked floor or nets within two stories or 30 ft, whichever is less, directly under erection work being performed.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass