A plumber finds that a sanitary pipe sleeve through a rated wall was omitted before the wall was closed. The crew proposes core drilling and leaving the annular space open. What should the superintendent require?
Correct Answer
D) Coordinate an approved penetration and firestopping detail before the pipe is installed
Penetrations through rated assemblies need approved openings and firestopping systems; leaving the annular space open can compromise the rating. Other choices ignore the rated assembly or use unapproved stuffing.
Why This Is the Correct Answer
Penetrations through rated assemblies need approved openings and firestopping systems; leaving the annular space open can compromise the rating. Other choices ignore the rated assembly or use unapproved stuffing.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
A rooftop unit schedule lists capacity in tons of cooling. In HVAC estimating, one ton of cooling equals what heat-transfer rate?
The bid form asks for a base bid and three alternates. How should the contractor submit alternate pricing?
A specification includes a $40,000 hardware allowance because final selections are pending. How is the allowance treated in the bid?
The earthwork section requires unit prices for unsuitable-soil removal. What is the contract-administration use of those unit prices?
Before the first progress payment, the owner requests a schedule of values. What is its main contract-payment function?
A signed change order is issued for added lobby millwork. Which contract effect should it state?
On the finish plan, locate room R358; then use the finish schedule. What remarks is listed?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A ready-mix load waits through a site access delay and arrives near the specification's maximum discharge time. Slump is low and the batch ticket shows no approved retarder. What should happen before placement?
Next Question
The owner selects light fixtures costing $12,000 more than the electrical fixture allowance. What should the contractor prepare?
