A plumber finds that a sanitary pipe sleeve through a rated wall was omitted before the wall was closed. The crew proposes core drilling and leaving the annular space open. What should the superintendent require?
Correct Answer
D) Coordinate an approved penetration and firestopping detail before the pipe is installed
Penetrations through rated assemblies need approved openings and firestopping systems; leaving the annular space open can compromise the rating. Other choices ignore the rated assembly or use unapproved stuffing.
Why This Is the Correct Answer
Penetrations through rated assemblies need approved openings and firestopping systems; leaving the annular space open can compromise the rating. Other choices ignore the rated assembly or use unapproved stuffing.
Why the Other Options Are Wrong
Option A: Core drill and leave the gap because the pipe is noncombustible
Choice A (Core drill and leave the gap because the pipe is noncombustible) is rejected because the option shifts to a different trade task; the tested Sleeve coordination function or field correction is Coordinate an approved penetration and firestopping detail before the pipe is installed.
Option B: The superintendent should cut the pipe smaller to avoid firestopping
In mechanical and plumbing, Cut the pipe smaller to avoid firestopping is the wrong selection for Sleeve coordination: it describes work from another assembly, while the Sleeve coordination item is asking for Coordinate an approved penetration and firestopping detail before the pipe is installed.
Option C: Base the sleeve coordination response on pack the gap with scrap insulation
The trap in C is Pack the gap with scrap insulation only. That selection is wrong because the option delays or omits the controlling step.
Memory Technique
Tag the scene with sleeve coordination: wrong actor or wrong timing means the fix is not Coordinate an approved penetration and firestopping detail before the pipe is installed.
Reference Hint
Open Principles and Practices of Commercial Construction, 11th Ed., 2024; use the index entry or section for "MEP penetrations through rated assemblies" to confirm that Penetrations through rated assemblies need approved openings and firestopping systems; leaving the annular space open can compromise the rating.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A ready-mix load waits through a site access delay and arrives near the specification's maximum discharge time. Slump is low and the batch ticket shows no approved retarder. What should happen before placement?
Next Question
The owner selects light fixtures costing $12,000 more than the electrical fixture allowance. What should the contractor prepare?
