The owner selects light fixtures costing $12,000 more than the electrical fixture allowance. What should the contractor prepare?
Correct Answer
D) A contract adjustment under the allowance and change-order provisions
When approved selections exceed the allowance, the contract is adjusted according to the allowance and change-order terms. Other choices ignore the cost difference or use the wrong contract mechanism.
Why This Is the Correct Answer
When approved selections exceed the allowance, the contract is adjusted according to the allowance and change-order terms. Other choices ignore the cost difference or use the wrong contract mechanism.
Why the Other Options Are Wrong
Option A: Base the allowance overrun response on a zero-cost RFI response
Choice A gives A zero-cost RFI response only. Its specific error: the option delays or omits the controlling step.
Option B: Classify the condition as a deductive change for the allowance overrun
Choice B (A deductive change for the allowance overrun) is rejected because it answers the Allowance overrun prompt with the wrong practical move.
Option C: Classify the condition as a new base bid
In procurement and contracting, A new base bid is the wrong selection for Allowance overrun: it names a financial document or payment mechanism, not the Allowance overrun action/result stated by A contract adjustment under the allowance and change-order provisions.
Memory Technique
Use the phrase "problem, control, result" for allowance overrun; the result side is A contract adjustment under the allowance and change-order provisions.
Reference Hint
Open Construction Project Management, 5th Ed. (2022); use the index entry or section for "Allowance adjustment" to confirm that When approved selections exceed the allowance, the contract is adjusted according to the allowance and change-order terms.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A plumber finds that a sanitary pipe sleeve through a rated wall was omitted before the wall was closed. The crew proposes core drilling and leaving the annular space open. What should the superintendent require?
Next Question
A supplier offers a cheaper roofing membrane after award, but the specified system has already been approved in the submittal log. What should happen before the cheaper product is purchased?