The owner selects light fixtures costing $12,000 more than the electrical fixture allowance. What should the contractor prepare?

Correct Answer

D) A contract adjustment under the allowance and change-order provisions

When approved selections exceed the allowance, the contract is adjusted according to the allowance and change-order terms. Other choices ignore the cost difference or use the wrong contract mechanism.

Answer Options
A
Base the allowance overrun response on a zero-cost RFI response
B
Classify the condition as a deductive change for the allowance overrun
C
Classify the condition as a new base bid
D
A contract adjustment under the allowance and change-order provisions

Why This Is the Correct Answer

When approved selections exceed the allowance, the contract is adjusted according to the allowance and change-order terms. Other choices ignore the cost difference or use the wrong contract mechanism.

Why the Other Options Are Wrong

Option A: Base the allowance overrun response on a zero-cost RFI response

Choice A gives A zero-cost RFI response only. Its specific error: the option delays or omits the controlling step.

Option B: Classify the condition as a deductive change for the allowance overrun

Choice B (A deductive change for the allowance overrun) is rejected because it answers the Allowance overrun prompt with the wrong practical move.

Option C: Classify the condition as a new base bid

In procurement and contracting, A new base bid is the wrong selection for Allowance overrun: it names a financial document or payment mechanism, not the Allowance overrun action/result stated by A contract adjustment under the allowance and change-order provisions.

Memory Technique

Use the phrase "problem, control, result" for allowance overrun; the result side is A contract adjustment under the allowance and change-order provisions.

Reference Hint

Open Construction Project Management, 5th Ed. (2022); use the index entry or section for "Allowance adjustment" to confirm that When approved selections exceed the allowance, the contract is adjusted according to the allowance and change-order terms.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.