A supplier offers a cheaper roofing membrane after award, but the specified system has already been approved in the submittal log. What should happen before the cheaper product is purchased?
Correct Answer
C) Submit and obtain approval under the substitution procedure
A post-award substitution must be reviewed and approved under the contract's substitution process before purchase or installation. Other choices bypass specified performance and review requirements.
Why This Is the Correct Answer
A post-award substitution must be reviewed and approved under the contract's substitution process before purchase or installation. Other choices bypass specified performance and review requirements.
Why the Other Options Are Wrong
Option A: Install it because lower cost always controls
In procurement and contracting, Install it because lower cost always controls is the wrong selection for Substitution request: it answers the Substitution request prompt with the wrong practical move.
Option B: The contractor should use it only on roof areas not visible from grade
The trap in B is Use it only on roof areas not visible from grade. That selection is wrong because it tries to bypass the Substitution request checkpoint.
Option D: Record it as an RFI with no product review
Choice D (Record it as an RFI with no product review) is rejected because the option does not produce the required Substitution request outcome, Submit and obtain approval under the substitution procedure.
Memory Technique
Picture a badge on the jobsite; substitution request is solved by the action that leads to Submit and obtain approval under the substitution procedure.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Substitution procedures" to confirm that A post-award substitution must be reviewed and approved under the contract's substitution process before purchase or installation.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
The owner selects light fixtures costing $12,000 more than the electrical fixture allowance. What should the contractor prepare?
Next Question
A contract clause is applied to this fact pattern: a room closeout team verifies 12 rooms per day. If 88 rooms remain, how many whole days are required?