A ready-mix load waits through a site access delay and arrives near the specification's maximum discharge time. Slump is low and the batch ticket shows no approved retarder. What should happen before placement?
Correct Answer
C) Verify acceptance under the specification with testing and authorization, or reject the load if it is out of limits
A delayed load near the time limit must meet the specification at discharge; testing and authorization are needed, and an out-of-limit load should be rejected. Other choices: ticket age alone, undocumented water, and unrecorded blending defeat quality control.
Why This Is the Correct Answer
A delayed load near the time limit must meet the specification at discharge; testing and authorization are needed, and an out-of-limit load should be rejected. Other choices: ticket age alone, undocumented water, and unrecorded blending defeat quality control.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
A rooftop unit schedule lists capacity in tons of cooling. In HVAC estimating, one ton of cooling equals what heat-transfer rate?
The bid form asks for a base bid and three alternates. How should the contractor submit alternate pricing?
A specification includes a $40,000 hardware allowance because final selections are pending. How is the allowance treated in the bid?
The earthwork section requires unit prices for unsuitable-soil removal. What is the contract-administration use of those unit prices?
Before the first progress payment, the owner requests a schedule of values. What is its main contract-payment function?
A signed change order is issued for added lobby millwork. Which contract effect should it state?
On the finish plan, locate room R358; then use the finish schedule. What remarks is listed?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
What does joint photographing mean in gypsum board finishing?
Next Question
A plumber finds that a sanitary pipe sleeve through a rated wall was omitted before the wall was closed. The crew proposes core drilling and leaving the annular space open. What should the superintendent require?
