A ready-mix load waits through a site access delay and arrives near the specification's maximum discharge time. Slump is low and the batch ticket shows no approved retarder. What should happen before placement?
Correct Answer
C) Verify acceptance under the specification with testing and authorization, or reject the load if it is out of limits
A delayed load near the time limit must meet the specification at discharge; testing and authorization are needed, and an out-of-limit load should be rejected. Other choices: ticket age alone, undocumented water, and unrecorded blending defeat quality control.
Why This Is the Correct Answer
A delayed load near the time limit must meet the specification at discharge; testing and authorization are needed, and an out-of-limit load should be rejected.
Why the Other Options Are Wrong
Option A: Place it quickly because the ticket proves it was once acceptable
The trap in A is Place it quickly because the ticket proves it was once acceptable. That selection is wrong because it points to Place it quickly because the ticket proves it was once acceptable, but.
Option B: Add water until slump returns and skip a ticket note
Choice B gives Add water until slump returns and skip a ticket note. Its specific error: the action skips the timing, documentation, or field-control step needed for Concrete time limits.
Option D: Blend the old load into the next truck without recording it
In concrete work, Blend the old load into the next truck without recording it is the wrong selection for Concrete time limits: it leaves the work at an informal or incomplete stage, while Concrete time limits requires Verify acceptance under the specification with testing and authorization, or reject the load if it.
Memory Technique
Tag the scene with concrete time limits: wrong actor or wrong timing means the fix is not Verify acceptance under the specification with testing and authorization, or reject the load if it is out of limits.
Reference Hint
Open The Contractor's Guide to Quality Concrete Construction, 4th Ed., 2018; use the index entry or section for "Ready-mix delivery acceptance" to confirm that A delayed load near the time limit must meet the specification at discharge; testing and authorization are needed, and an out-of-limit load should be rejected.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
What does joint photographing mean in gypsum board finishing?
Next Question
A plumber finds that a sanitary pipe sleeve through a rated wall was omitted before the wall was closed. The crew proposes core drilling and leaving the annular space open. What should the superintendent require?